Communities Protest Cancellation of N147.6bn Road Contract in Katsina

74
Spread the love

Residents of communities along Katsina-Kankara-Dutsinma-Maraba Kankara road in Katsina State have condemned in very strong terms, the alleged cancellation of a N147.6 billion contract for the full rehabilitation of the road by the Ministry of Works.

The residents who are pleading with   President Bola Ahmed Tinubu to intervene by directing a reversal of the cancellation, have however accused the Minister of works, David Umahi, of cancelling the contract which was awarded to an indigenous firm, Vipan Global Resources Limited, after fulfilling all the requisite requirements, has a completion period of 24 months. 

One of the residents, Mohammed Sani, a community leader, who spoke on behalf of others told journalists in Abuja that the road project was awarded to the Firm on 5th April, 2024 with Contract Number 8489.

According to Sani, a certificate of no objection was duly issued by the Bureau of Public Procurement as well as an approval by the Federal Executive Council (FEC).

Documents displayed by the residents include all the bidding documents, an award letter, FEC approval, acceptance letter, Engineer’s Order to begin work, and site handover letter, among others.

The Engineer’s Order signed by Engr O.U Bakare, instructed the Firm to commence work with effect from 15 April, 2024 with a directive that the work be completed on 14 April, 2026.

Also, in an official letter duly signed by Engineer Tahir B.G, Federal Controller in Katsina State, the federal ministry of work handed over the road to the contractor on 24 April 2024.

Speaking further, Sani disclosed that a senior official of the ministry confirmed that the Managing Director of the Company and officials of the federal ministry of works jointly signed an agreement for the road project on 10th May 2024.

Sani said, “We were told that the firm wrote a letter of request for advance payment guarantee to the ministry and mobilised to site and commenced work in line with the contractual terms.

“It was while waiting for payment that the ministry issued a letter on 16 July, 2024 asking the firm to stop the road project and vacate the site immediately.

“In the letter signed by Engr Goni Mohammed, Director of Highways North West, on behalf of the federal ministry of works, the contract was stepped down, citing lack of funds.

“The claim was faulted by many officials of the ministry because there is a N10.9billion budgetary provision for it in the 2024 budget.

The residents from communities along the road, however alleged that the action of the Federal Ministry was carried out  politically,  even as they took a swipe at  the minister for condoning acts that could saw a seed of discord between the federal government and the north. 

They wondered why Umahi cancelled a project in the north and did not cancel any from the south as if he is trying to pit the north against the president.

Investigation however, revealed that the project was cancelled due to funds paucity, just as a source at the ministry added that the contractor had sunk huge sums of money into the project and was not prepared to incur losses.

When contacted, a senior staff of the works Ministry confirmed that there are similar road projects awarded by the works ministry most of which have less budgetary provisions than the one in question.

The staff said, “These projects include the rehabilitation and dualization of Enugu-Abakaliki-Ogoja road awarded to Reinforced Global Resources Limited for N183.6bn with a budgetary provision of N2.5bn in the 2023 supplementary budget with 24-month completion period.

“There is also the rehabilitation of Ugep-Abaomoge-Opkosi road in Cross River state awarded to Reinforced Global Resource Limited for N54.6bn with a budgetary provision of N2.5bn in the 2023 supplementary budget with 24-month completion period.

“There is also the construction of Malando-Garin Baka-Ngaski-Wara  road in Kebbi state awarded to Epsilon Sky Global Engr Limited  for N96.1bn with a budgetary provision of N4bn; and the construction of Benin by-pass in Edo state awarded to CCECC for N230bn with the provision of N2.5bn made in the budget.

“Others are, the  construction of Benin-Agbor road awarded to China Harbour Construction Company at N202bn without budgetary provision, and construction of Kaima-Kishi road section 1 in Kwara state at the cost of N50.6bn awarded to IGEE Engineering Company Limited without budgetary provision.

“Another one is the contract for the construction of a 23-span flyover bridge project at Ele-Obinagu Junction, along Enugu-Abakaliki Road awarded to Reinforced Global Resources Limited for N19.4bn with a budgetary provision of N2.5bn and a 24-month completion period.

“There is also the contract for the reconstruction of Bida-Lemu-Wushishi-Zungeru Road in Niger state awarded to Gerawa Global Engineering for N66.9bn for which there is a budgetary provision of N2bn in the 2023 supplementary budget and a 24-month completion period; construction of Otukpo-Nasarawa road in Benue state awarded to Wizchino Engineering Limited for N198.8bn in the 2023 supplementary budget with a 36-month completion period.

“Others are contract for the rehabilitation of Abeokuta-Ibaro/Ilaro road in Ogun state awarded to Strabic Construction Company at N57bn with about N71.7m budgetary provision; and, rehabilitation of Ore-Ondo-Akure Road in Ondo state awarded to Civil & Building Construction (CBC) Global for N134.8bn with provision for N4.7bn made in the budget.”


Spread the love